Progress Report

October 22, 2015

As of today, the scaffolding system and enclosure has been completed.  The crew began demolition of existing cap metal and removal of chicken wire glass panels on Wednesday, 10/21. Debris netting to protect the stained glass is being installed in sections below the skylight panels prior to their demolition. The project is on schedule to meet the November 1st milestone for removal of the historic glass panels.